3 Celina Parkway reconstruction Project: The project follows Celina Parkway from Outer Loop FM 428. The project will replace the asphalt pavement. Update: The project is in the design phase. • Timeline: TBD • Cost: $2.8 million Project: The project will expand the two-lane roadway to a four-lane roadway between Dallas North Tollway and Coleman Street. The project includes concrete curb and gutter roadway, underground drainage improvements and 12-inch water line. Update: The project is in the design phase. The project was projected to start in late 2024, early 2025 but there were delays related to right-of-way and easement acquisitions. • Timeline: late 2025/early 2026-fall 2027 • Cost: $27.79 million • Funding source: town of Prosper 5 Prosper Trail improvements • Funding source: city of Celina 4 First Street widening Project: The project will be a full reconstruction of pavement and bridge replacement at Wilson Creek crossing. The new pavement will be a four-lane divided roadway. The proposed budget will include 8-foot sidewalks with traffic railing separation and pedestrian

project Oct. 2026 • Cost: $73 million total • Funding source: city of Celina

rail. The project spans Coit Road to Custer Road. Update: The project is in the design phase, which is about 75% complete. • Timeline: summer 2026-summer 2027 • Cost: $13.45 million

8 Sunset Boulevard asphalt improvements Project: The project will replace the asphalt pavement of Sunset Boulevard from Preston Road to Coit Road. Update: The contractor is currently working on the installation of the sanitary sewer line. Construction is on track and about 60% complete. • Timeline: estimated completion February 2026 • Cost: $4.2 million • Funding source: city of Celina 9 First Street construction Project: First Street is being widened to a four-lane roadway of concrete pavement with medians from Stuber Elementary School to North Dallas Parkway. Update: The project is under construction and is nearing completion. • Timeline: spring 2023-fall 2025 • Cost: $30.89 million • Funding source: town of Prosper

• Funding source: town of Prosper 6 Gee Road improvements

Project: The project, which spans US 380 to FM 1385, includes paving, drainage and a foot bridge over Doe Branch drainage crossing and Dow Branch Tributary. Update: The project is in the design phase, which is about 91% complete. • Timeline: TBD • Cost: $21.9 million • Funding source: town of Prosper

Ongoing projects

7 Celina Parking garage construction Project: The project will construct about a 400 space parking garage on the east side of Arizona between Walnut Street and Pecan Street. Update: The parking garage is under construction. It is part of the downtown center construction package. The entire project is about 30% complete. • Timeline: parking garage completion fall 2025; entire

A first of its kind is here. Welcome to advanced care in North Texas. Where wellness has been reinvented and every visit is transformed into an experience. Explore sculpture gardens made for healing, luxurious maternity rooms, a park the whole family will enjoy, free valet parking and much more.

The power to live better ®

BSWHealth.com/PGAParkway

Physicians provide clinical services as members of the medical staff at one of Baylor Scott & White Health’s subsidiary, community or affiliated medical centers and do not provide clinical services as employees or agents of those medical centers or Baylor Scott & White Health. ©2025 Baylor Scott & White Health. 99-EST-1108561-BSWPGACreativeCampaign_Launch

17

PROSPER - CELINA EDITION

Powered by