Prosper - Celina | September 2025

Transportation

BY SAMANTHA DOUTY

3 Coit Road resurfacing Project: The project includes the asphalt resurfacing of Coit Road in three segments. These segments are CR 100 from Preston Road to CR 97, CR 90 from CR 92 to CR 98, and CR 97 from Lynn Stambaugh Parkway to CR 134. Update: The project is in the design phase and is ready for bidding. • Timeline: estimated completion is September 2026 • Cost: $3.49 million • Funding source: city of Celina 4 Legacy Drive construction Project: Legacy Drive from Honey Creek Way to Carey Road will be constructed to a two-lane concrete roadway including a bridge. Update: The project is 90% complete with planning and is on hold awaiting construction funding. • Timeline: TBD • Cost: $11.73 million

8 First Street reconstruction Project: First Street is being redone from Stuber Elementary School to Dallas Parkway. The project includes four-lanes of concrete pavement and median landscaping. Update: The project is under construction and should be completed later this year. • Timeline: spring 2023-November 2025 • Cost: $30.89 million • Funding source: town of Prosper 9 US 380 widening Project: US 380 is being widened by TxDOT the Collin and Denton County dividing line to Loop 288. It is being expanded from a four-lane divided roadway to a six-lane divided roadway. The project also includes the construction of overpasses at Legacy Drive, Teel Parkway and FM 423. Update: The project is under construction and should wrap next year. • Timeline: early 2022-April 2026 • Cost: $175.66 million • Funding source: TxDOT, other entities

32% complete. • Timeline: late 2025-fall 2027 • Cost: $27.79 million • Funding source: town of Prosper

Upcoming projects

455

MARILEE RD.

LEGACY DR.

1 Marilee Road reconstruction Project: The project spans Marilee Road from Preston Road to Dallas Parkway. The project is shared with the city of Gunter, Grayson County, Collin County, city of Celina and the adjacent subdivision developers. The project will be a full depth reclamation of the existing asphalt roadway. Update: The project is in the design phase. • Timeline: TBD • Cost: $8.7 million • Funding source: city of Celina, other entities 2 Preston Road lighting installation Project: The project will include arterial lighting installation along Preston Road from Legacy Drive to Grayson County line. Update: The project is in the design phase with 100% of the plans complete. The project is on hold until the Texas Department of Transportation’s funding is available. • Timeline: TBD • Cost: $740,000 • Funding sources: city of Celina, TxDOT

6

2

1

134

Ongoing projects

3 C R 100

428

E. SUNSET BLVD.

Celina

6 Sunset Boulevard asphalt improvements Project: The project is replacing the asphalt pavement and installing sanitary sewer along Sunset Boulevard from Preston Road to Coit Road. Update: The project is under construction. • Timeline: estimated completion February 2026 • Cost: $4.2 million Project: Coit Road from First Street to Prosper Trail is being widened from a four-lane roadway to a six-lane divided concrete roadway. This is the first phase of redeveloping Coit Road. Update: The project is under construction, which started this summer. • Timeline: summer 2025-summer 2026 • Cost: $23.64 million • Funding source: town of Prosper • Funding source: city of Celina 7 Coit Road construction

455

PRESTON RD.

CAREY RD.

4

HONEY CREEK WAY

FRONTIER PKWY.

1385

• Funding source: city of Celina 5 First Street widening

W. PROSPER TRL.

Prosper

7

8

5

Project: First Street will be widened from a two-lane rural roadway to a four-lane divided suburban roadway between Dallas North Tollway to Coleman Street. Update: The project is in the design phase and will start construction later this year or early next year. Design is about 65% complete while utility relocations

FIRST ST.

9

380

MAP NOT TO SCALE N