5 Riverside Middle School Schedule: October 2024-December 2025 Scope of work: 60,000-square-foot campus addition, new competition gym and fine arts facilities Status: 55% complete 6 Creekside Middle School Schedule: October 2024-December 2025 Scope of work: 60,000-square-foot campus addition, new competition gym and fine arts facilities Status: 50% complete 7 Bastrop High School Schedule: May 2025-December 2027 Scope of work: 38,000-square-foot addition in permitting phase, new classroom wing and continued renovations Status: 11% complete 8 BISD police and operations facility Schedule: January 2025-March 2026 Scope of work: 55,000-square-foot facility to serve police administration, maintenance, custodial, groundskeeping, warehouse and the district’s print shop Status: 42% complete

94

COLORADO RIVER

71

CHAMBERS ST.

21

7

3 5

2

71

1

21

304

71

6 4

OLD AUSTIN HWY.

20

8

VOSS PKWY.

MAP NOT TO SCALE N

Track the latest on BISD bond projects

In August, Bastrop ISD marked the opening of its newest elementary school, Adelton—one of several projects funded by more than $500 million in bond initiatives approved in 2021 and 2023.

2 Mina Elementary Phase 2 Schedule: January 2025-May 2026 Scope of work: 35,500-square-foot campus expansion Status: 34% complete 3 4 Bastrop and Cedar Creek Middle School expansions Schedule: December 2024-December 2025 Scope of work: 21,000-square-foot addition to each campus Status: 45% complete

Bond projects

1 Adelton Elementary School Schedule: June 2024-August 2024 Scope of work: new 105,000-square-foot elementary school Status: 100% complete

Protecting You, Your Business & Your Family

YOUR NEW PLACE TO CALL HOME. Call Us Today! 512-409-3342 ringelbrymerlaw.com

Learn More

1006 Home Depot Way | Bastrop, TX | 512-270-7239

9

BASTROP - CEDAR CREEK EDITION

Powered by