Transportation
BY VANESSA HOLT
2 Lake Woodlands Drive at Gosling Road intersection improvements Project: The project will extend turn lanes to improve mobility and safety from eastbound Lake Woodlands Drive onto northbound Gosling Road and from westbound Lake Woodlands Drive onto southbound Gosling Road. Update: Engineering design was complete in October, Precinct 3 officials said. • Cost: $40,000 (design) • Timeline: June-early September (design), utility relocation (October-TBD) • Funding source: Montgomery County road bond 3 Research Forest Drive at Gosling Road turn-lane extension Project: The project will extend dual left-turn lanes from westbound Research Forest to southbound Gosling and from Gosling to Research Forest in both directions. Update: Engineering design was completed as of Oct. 10, Precinct 3 officials said. The next phase of the project will be coordinating utility relocations. • Cost: $25,500 (design) • Timeline: June-August (design), September-TBD (utility coordination) • Funding source: Montgomery County road bond 4 Woodlands Parkway at Kuykendahl Road turn-lane extension Project: The project will add a left-turn lane and extend lane storage from northbound Kuykendahl Road to westbound and eastbound Woodlands Parkway. Update: Engineering design work was completed as of September, Precinct 3 officials said. • Cost: $88,240 (design) • Timeline: June-August (design), utility relocation (September-TBD) • Funding source: Montgomery County road bond
construction was nearing completion in October, according to information from Montgomery County Precinct 3. • Cost: $50,000 (design) • Timeline: June-August (design), September-October (construction) • Funding source: Montgomery County road bond 6 Hwy. 242 widening Project: TxDOT is using existing right of way on Hwy. 242 between FM 1488 and I-45 to widen lanes and restripe the intersections. Update: As of the most recent information released by TxDOT in October, the project being carried out by Posillico Civil, Inc. was 68% complete. • Cost: $29.11 million • Timeline: Oct. 23, 2023-fourth quarter 2026 • Funding sources: federal, state funds
1488
45
242
6
GREENBRIDGE DR.
1
VISION PARK BLVD.
The Woodlands
3
RESEARCH FOREST DR.
4
2
5
LAKE WOODLANDS
KUYKENDAHL RD.
8
7
E. PANTHER CREEK DR.
Completed projects
7 Grogans Mill Road and Lake Woodlands Drive turn-lane extension Project: The project extends the left-turn lane to the median opening on northbound Grogans Mill Road onto westbound Lake Woodlands Drive. Update: Engineering design was completed in August and the project was completed in October, according to information from Precinct 3. • Cost: $22,500 (design), $84,744 (construction) • Timeline: Construction September-October • Funding source: Montgomery County road bond 8 Lake Woodlands Drive at East Panther Creek Drive turn-lane extension Project: The project extended the left-turn lane from westbound Lake Woodlands Drive onto southbound East Panther Creek Drive. Update: Construction has been completed. • Cost: $22,500 (design), $116,057 (construction) • Timeline: Completed in September • Funding sources: Montgomery County road bond
GROGANS MILL RD.
MAP NOT TO SCALE N
Upcoming projects
99 TOLL
Spring 1 Research Forest Drive at Greenbridge Drive turn-lane extension Project: The project will extend and widen the left- turn lane from eastbound Research Forest Drive to northbound Greenbridge Drive. Update: Engineering design was completed, and construction will begin in October, according to Precinct 3. • Cost: $10,500 (design) • Timeline: June-August (design), October-TBD (construction) • Funding source: Montgomery County road bond
Ongoing projects
5 Grogans Mill Road at Research Forest Drive right-turn improvements Project: The project will extend a right-turn lane from northbound Grogans Mill Road onto eastbound Research Forest Drive. Update: Engineering design was completed and
INSURED
112
A CLEAN KITCHEN Stts He
FREE OVEN CLEANING with Bi-Weekly Service
• 1 English-speaking maid per job • All supplies included • 24-hour satisfaction guarantee • No contracts, no hidden fees
(281) 630-1216
LemurCleaning@gmail.com | www.LemurCleaning.com
37
THE WOODLANDS EDITION
Powered by FlippingBook