Bay Area Edition | December 2025

BY HALEY VELASCO

LEAGUE CITY PWKY.

Commercial

Mapping it out

E. BAY AREA BLVD.

Mixed-use Single-family residential

MAPLE LEAF DR.

Grand Parkway will be in League City’s western portion, which is largely undeveloped, as previously reported by Community Impact . Upcoming developments on the west side include residential spaces, mixed-use, commercial spaces, parks and drainage.

Drainage/detention

Civic Open spaces/parks

Industrial Flex

517

SOURCE: LEAGUE CITYCOMMUNITY IMPACT NOTE: ALL UPCOMING DEVELOPMENTS HAVE NOT YET BEEN BUILT OUT.

Planned roads

MC FARLAND RD.

N

What's next?

and alleviate some of the congestion issues that will come with all the new growth,” League City City Manager John Baumgartner said. Residents of League City can stay informed on the project and its progress by visiting www.leaguecitylistens.com/grandparkway.

that drivers: • Don’t use phones • Slow down • Obey warning signs Section B-1 is slated to open to trac in the summer or fall of 2031, Shirley said. “In 2031, we’ll have a new roadway to drive on

Segment B-1 is still in its procurement phase, meaning TxDOT is evaluating and getting set to select a contractor to design and build the segment. After a contract is executed, design and project mobilization will take place in the summer, fall and winter of 2026, Shirley said. When construction occurs, Shirley requests

The timeline

SOURCE: TEXAS DEPARTMENT OF TRANSPORTATIONCOMMUNITY IMPACT

2026

2027

2031

July: contract execution

Late summer, fall and winter: design and project mobilization

February: technical, price proposals due

Late April: conditional award

Spring: construction

Summer or fall: Section B-1 of Grand Parkway opens to trac

17