Sugar Land - Missouri City Edition | April 2022

TRANSPORTATIONUPDATES Retiming of Hwy. 6 traffic signals gets completed

COMPILED BY HUNTER MARROW

ONGOING PROJECTS

VICKSBURG BLVD.

The city of Missouri City completed work on April 1 to retime 16 signalized intersections along 6.7 miles of Hwy. 6 from Creekmont Drive to Colonial Lakes Drive. The work, which started in early March, is designed to improve traffic progression and reduce travel time across that section of the highway, said Shashi Kumar, the city’s engineer and director of public works, during a March 7 City Council presentation. With the signals retimed, the city anticipates reducing travel time by an average of 42 seconds eastbound and 39 seconds westbound, officials said. From Creekmont Drive to Colonial Lakes Drive, the aver- age drive will now take 10 minutes and 11 seconds instead of 10 minutes and 57 seconds during morning traffic peaks. Similar results will be seen the opposite direction during evening rush hour, according to the city. “Those numbers don’t sound like a lot, but when you’re looking at over 60,000 vehicles that are saving that time, it starts to add up,” Assistant Engineer Jeremy Davis said. The work took place because the intersection at Colonial Lakes Drive faced over 50,000 vehicles per day in 2021, up from 26,000 10 years prior. Other intersections farther south along Hwy. 6 saw greater numbers from 49,600 vehicles per day in 2011 up to 60,800 in 2021, according to traffic counts recorded by Missouri City. In addition, the city has needed to maintain additional traffic signals over the years. In 1998, Missouri City

LAKE OLYMPIA PKWY.

AUSTIN PKWY.

6

2234

1092

LAKESHORE HARBOUR BLVD.

COLONIAL LAKES DR.

SIENNA PKWY.

N

Vicksburg corridor recommendations A project intending to improve safety along a traffic corridor on Vicksburg Boulevard from Lake Olympia Park- way to Lakeshore Harbour Boulevard is now underway. By the end of April, Missouri City will implement several traffic safety recommendations, including narrowing lane widths to reduce speeds and installing rect- angular rapid flashing beacons and dynamic speed feedback signs. Timeline: March-end of April Cost: $90,000 Funding sources: Missouri City, Metropolitan Transit Authority of Harris County

LAKE OLYMPIA PKWY.

6

OILFIELD DR.

UNIVERSITY BLVD.

CREEKMONT DR.

SIENNA PKWY.

N

maintained five signals, but in 2022, the city maintains 63 signals, according to the March 7 presentation. The signal retiming is only a short-termmeasure, however. The long-term approach will be to add additional lanes to that section of Hwy. 6, officials said at the meeting. The approximate cost of the retiming project was $250,000, Kumar said in an email. The project was funded through the city’s fiscal year 2020-21 budget; however, the projected start was delayed to obtain more accurate traffic counts reflective of average traffic volumes, due to the pandemic potentially skewing data.

ALL INFORMATION ON THIS PAGE WAS UPDATED AS OF MARCH 22. NEWS OR QUESTIONS ABOUT THESE OR OTHER LOCAL TRANSPORTATION PROJECTS? EMAIL US AT SLMNEWS@COMMUNITYIMPACT.COM.

2022 Kia EV6

The all-electric EV6 is designed to inspire with a driver centric cockpit, Dual Panoramic Screens, an available Augmented Reality Head-Up Display, the spaciousness of a 5-passenger crossover, and up to 310miles of EPA estimated all-electric range on a single charge. Innovation that inspires.

STARTING AT $40,900

0-60 MPH in 4.6 seconds, faster than a Porsche Cayenne Coupe

Gain 217 miles of range with only 18minutes of fast charging

Fort Bend

FortBendKia.com

9

SUGAR LAND - MISSOURI CITY EDITION • APRIL 2022

Powered by