Development
BY SAMANTHA DOUTY
• Cost: $775,000 • Funding sources: city of Frisco, external funding 10 Fields hike and bike trail construction Project: A new hike and bike trail will be added from Legacy Drive to Panther Creek Parkway. The new trail will connect to the existing PGA trail and the planned Panther Creek hike and bike trail. Update: The project is in the design phase. • Timeline: expected completion date is early 2026 • Cost: TBD • Funding sources: TBD 11 Panther Creek hike and bike trail construction Project: This will be a new hike and bike trail that connects the new Fields hike and bike trail and another portion of the Panther Creek trail, which is currently under construction. Update: The project is in the planning phase. • Timeline: TBD • Cost: TBD • Funding sources: TBD
1 Cottonwood hike and bike trail construction
4 Friendship Trail creation Project: The project will create a new hike and bike trail north of Shady Brook Lane from FM 423 to short of County Down Lane. It will connect to the existing Trails of West Frisco trail. Update: The project is in the planning phase. • Timeline: TBD • Cost: TBD • Funding sources: TBD 5 Brinkmann hike and bike trail extension Project: The new Brinkmann hike and bike trail will connect to the existing College Parkway trail and extend north of Main Street. Update: The project is in the planning phase. • Timeline: TBD • Cost: TBD • Funding sources: TBD 6 Parvin Branch underpass addition Project: A new hike and bike trail is being extended along the Parvin Branch trail under Preston Road. Update: The trail is under construction. • Timeline: mid 2023-mid 2025 • Cost: $1.5 million • Funding sources: city of Frisco, external funding
7 Panther Creek Trail creation Project: A new trail is being added along Panther Creek connecting it to some existing trails north of Eldorado Parkway from Preston Road to BNSF. Update: The project is under construction and is expected to be completed later this year. • Timeline: mid 2024-end of 2025 • Cost: $3.6 million • Funding sources: city of Frisco 8 Roger’s Settlement Park and trail addition Project: A new neighborhood park and hike and bike trail is being added near Eldorado Parkway. It will extend from BNSF to Eldorado Parkway. Update: The project is under construction and is expected to be completed early next year. • Timeline: end of 2024-early 2026 • Cost: $7 million • Funding sources: city of Frisco, external funding 9 Independence Trail extension Project: The project will create a new hike and bike trail connecting to the existing Independence Park trail. Update: The project is under construction and is
UNIVERSITY DR.
Map key
380
PGA PKWY.
Existing Trail New Trail Park
Project: A new trail will be added from Frisco Street to BNSF. It will be a hike and bike trail. It will connect to the existing Cottonwood hike and bike trail. Update: The project is in the design phase and will start construction next year. • Timeline: early 2026-mid 2027 • Cost: $1.4 million • Funding sources: city of Frisco 2 Cottonwood hike and bike trail extension Project: A new hike and bike trail will be created from
ROCKHILL PKWY.
6
VIRGINIA PKWY.
10
DNT TOLL
PANTHER CREEK PKWY.
11
7
9
COTTONWOOD CREEK TRL.
8
2478
COMMUNITY TRL.
FRISCO ST.
ELDORADO PKWY.
5
289
4
2
the existing Cottonwood trail to Main Street. Update: The project is in the planning phase. • Timeline: TBD • Cost: TBD • Funding sources: TBD 3 Iron Horse trail creation
1
KING RD.
MAIN ST.
Frisco
COLLEGE PKWY TRL.
BIG BLUESTEM TRL.
ROLATER RD.
STONEBROOK PKWY.
SRT TOLL
Project: The Iron Horse trail will connect to the existing Big Bluestem trail and extend to Rock Creek Parkway. Update: The project is in the design phase and will connect to Grand Park. • Timeline: early 2026-mid 2027 • Cost: $7.5 million • Funding sources: city of Frisco, external funding
LEBANON
3
LEWISVILLE LAKE
ROCK CREEK PKWY.
WARREN PKWY.
expected to be completed later this year. • Timeline: end of 2024-September 2025
SRT TOLL
423
MAP NOT TO SCALE N
LITTLE ELM 27100 Hwy 380 (972) 347-9630
LOWRY 4100 E US 380 (972) 540-2500 THE COLONY 4901 Hwy 121 (214) 469-2113
ALLEN 1839 N Central Expressway (972) 908-3488
Powered by FlippingBook