Frisco | August 2025

BY SAMANTHA DOUTY

9 Eldorado Parkway traffic light installation Project: A traffic light will be installed at the Eldorado Parkway and Research Road intersection. Update: The project is under construction and will be completed this year. • Timeline: end of 2024-September 2025 • Cost: $250,000 • Funding source: city of Frisco 10 Panther Creek Parkway extension Project: Panther Creek Parkway is being extended from Dallas North Tollway to Preston Road. It will construct a six-lane divided roadway. Update: The project is under construction and is expected to be completed at the end of this year, according to the city’s capital improvement website. • Timeline: early 2024-end of 2025 • Cost: $56.4 million • Funding sources: city of Frisco, Collin County 11 Hillcrest Road construction Project: Hillcrest Road will become a four-lane roadway from PGA Parkway to Panther Creek Parkway. Update: The project is currently under construction and is expected to be completed by the end of September. • Timeline: early 2024-September 2025 • Cost: $5.99 million • Funding sources: city of Frisco

expected to start construction mid 2026 • Timeline: mid 2026-late 2027 • Cost: $15 million • Funding source: city of Frisco 4 Teel Parkway widening

out for construction bids by the end of the year. • Timeline: end of 2025-early 2027 • Cost: $3.9 million • Funding source: city of Frisco, external funding

Ongoing projects

Project: Teel Parkway will be widened from a two-lane roadway to a four-lane roadway from Stafford Middle School to Oliver Branch Road. Update: The project is now in the design phase and is expected to start construction later this year. • Timeline: August 2025-end of 2026 • Cost: $12 million • Funding source: city of Frisco 5 Rolater Road traffic signal installation Project: A new traffic signal will be added to the Rolater Road and Valley Brook Drive intersection. Update: The project is in the design phase with construction bids expected to go out later this year. • Timeline: September 2025-mid 2026 • Cost: $300,000 • Funding source: city of Frisco 6 Gaylord Parkway roundabout addition Project: A new roundabout will be added to the Ohio Drive and Gaylord Parkway intersection. Update: The project is in the design phase and will go

7 Main Street pedestrian plaza construction Project: Main Street from BNSF Railroad to North County Road and Fourth Street from Main Street to Elm Street are under construction to increase sidewalk widths and create a pedestrian plaza. Update: This portion of the project is under construction and is expected to be completed by the end of this year. The overall project will be completed in 2026. • Timeline: early 2024-late 2025 • Cost: $20.54 million • Funding source: city of Frisco 8 Main Street traffic signal installation Project: A new traffic signal will be added to the Main Street and Fourth Street intersection. Update: The project is under construction. • Timeline: mid 2025 - late 2025 • Cost: $250,000 • Funding source: city of Frisco

24/7 EMERGENCY CARE for Dogs & Cats

THEY’RE BACK IN SCHOOL. TIMETOFOCUSON You.

Where High Quality Medicine Meets Compassionate Care.

Plastic Surgery Medspa Wellness & Weight loss Now oering GLP-1 treatment under a doctor’s care

WALK-INS WELCOME!

Sean M. Hill, M.D. FACS Board Certied Plastic Surgeon 214.937.4879

(469) 598- 1944

9560 Legacy Drive, Suite 200, Frisco, TX, 75033

17

FRISCO EDITION

Powered by