Update: Engineering design was underway and the project was starting the construction planning phase as of early December, officials said. • Timeline: Construction is slated to begin in summer 2026. • Cost: $52,500 (design) • Funding source: Montgomery County road bond 5 Grogan’s Mill Road at North Millbend Drive intersection upgrade Project: The project will redesign traffic signal and intersection layout, upgrade traffic signal facilities, replace pavement in the intersection as needed and restripe the intersection, Precinct 3 officials said in December. Update: The project was in the engineering design phase in December. • Timeline: Construction is estimated to start in the summer. • Cost: $52,500 (design) • Funding source: Montgomery County road bond 2978

Upcoming projects

1 Lake Woodlands Drive at Gosling Road intersection improvements Project: The project will extend turn lanes from eastbound Lake Woodlands Drive onto northbound Gosling Road. It will also extend turn lanes from westbound Lake Woodlands Drive onto southbound Gosling Road. Update: Engineering design was complete in early December and utility coordination was ongoing, Precinct 3 officials said. • Timeline: Construction will begin in early 2026. • Cost: $40,000 (design) • Funding source: Montgomery County road bond 2 Research Forest Drive at Gosling Road turn lane extension Project: The project will extend dual left-turn lanes from westbound Research Forest Drive to southbound Gosling Road. They will also be extended from Gosling Road to Research Forest Drive in both directions. Update: Engineering design was complete and utility coordination was ongoing as of early December, officials said. • Timeline: Construction will begin in early 2026. • Cost: $25,500 (design) • Funding source: Montgomery County road bond 3 Woodlands Parkway at Kuykendahl Road turn lane extension Project: The project will add a left-turn lane and extend lane storage from northbound Kuykendahl Road to Woodlands Parkway. Update: Engineering design was complete and new signal equipment was ordered as of early December, Precinct 3 officials said. • Cost: $88,240 (design) • Timeline: Construction will begin in spring or summer 2026. • Funding source: Montgomery County road bond 4 Grogan’s Mill Village Center signalization Project: A traffic signal will be replaced at the intersection of Grogan’s Mill Road and the entrance to the Grogan’s Mill Village Center, according to Precinct 3.

242

45

The Woodlands

2

RESEARCH FOREST DR.

3

1

LAKE WOODLANDS

KUYKENDAHL RD.

6

7

E. PANTHER CREEK DR.

WOODLANDS PKWY.

ASHLANE LN.

5

9

N. MILLBEND DR.

GROGANS MILL RD.

BRANCH CROSSING DR.

4

8

Completed projects

E. BENDERS LANDING BLVD.

6 Lake Woodlands Drive at East Panther Creek Drive turn-lane extension Project: The project extended the left-turn lane from westbound Lake Woodlands Drive onto southbound East Panther Creek Drive. Update: As of a November update, the project was completed. • Timeline: June-August (design), September-November (construction) • Cost: $22,500 (design), $116,057 (construction) • Funding source: Montgomery County road bond 7 Grogans Mill Road at Lake Woodlands Drive turn-lane extension Project: The project extended the left-turn lane to the median opening on northbound Grogans Mill Road and the turn onto westbound Lake Woodlands Drive. Update: As of a November update, the project was completed. • Timeline: September-November • Cost: $22,500 (design), $84,744 (construction) • Funding source: Montgomery County road bond

MAP NOT TO SCALE N

8 Rayford Road at East Benders Landing Project: A merge lane was created for vehicles leaving Benders Landing Estates.

Update: The project was completed. • Timeline: September-November • Cost: $38,318 (construction and striping)

• Funding source: Montgomery County road bond 9 Woodlands Parkway at Branch Crossing Drive turn lane extensions Project: The left-turn lane was extended from westbound Woodlands Parkway to southbound Branch Crossing Drive. It also extended a left-turn lane from Branch Crossing Drive onto eastbound Woodlands Parkway. Update: The project was completed in early December. • Timeline: fall-December. • Cost: $58,000 (design), $310,876 (construction) • Funding source: Montgomery County road bond

Dive Into Winter Fun! Snowball Frenzy at The Pod Aquatics

YOUR LOCAL LEGO SUPERSTORE ® largest selection of Lego around! earn rewards on every purchase SUPERSTORE

convenient parking & access friendly & Helpful service locally owned & operated

January 17, 2026 — 1 PM to 4 PM

Registration deadline: Jan 15th

• Water games and relay races • Open swim

$25 .00 Per Person $40.00 Per Family

Mon-Fri: 11am-7pm Sat: 10am-6pm Sun: Noon-5pm 12/24: 10am - 2pm 12/25: Closed 12/26: Boxing Day Specials!

• Activities & crafts • Snacks & drinks • Prizes and ra€le

GIFT CARDS AVAILABLE

Swim@PodAquatics.com | 281-719-0816 | podaquatics.com 26447 Hanna Road, Oak Ridge North, 77385

385A Sawdust Rd Spring, TX 77380 346-771-LEGO 346-771-LEGO 385A Sawdust Rd Spring, TX 77380

33

THE WOODLANDS EDITION

Powered by