Transportation
BY VANESSA HOLT
and from Gosling to Research Forest in both directions. Update: Engineering design was nearing completion in September. • Cost: $25,500 (design) • Timeline: June-August (design), September-TBD utility coordination) • Funding source: Montgomery County road bond 5 Woodlands Parkway at Kuykendahl Road turn-lane extension Project: The project will add a left-turn lane and extend lane storage from northbound Kuykendahl Road to westbound and eastbound Woodlands Parkway. Update: Engineering design work was completed as of September. • Cost: $88,240 (design) • Timeline: June-August (design), utility relocation (September-TBD) • Funding source: Montgomery County road bond
Magnolia
1488
45
WINDSOR LAKES BLVD.
EGYPT LN.
242
TAMINA DR.
2
GREENBRIDGE DR.
VISION PARK BLVD.
The Woodlands
4
RESEARCH FOREST DR.
DAVID MEMORIAL DR.
5
3
1
LAKE WOODLANDS
BRANCH CROSSING DR.
7
6
E. PANTHER CREEK DR.
2978
GROGANS MILL RD.
Ongoing projects
MAP NOT TO SCALE N
6 Grogans Mill Road and Lake Woodlands Drive turn-lane extension Project: The project will extend the left-turn lane to the median opening on northbound Grogans Mill Road onto westbound Lake Woodlands Drive. Update: Engineering design was completed in August. • Cost: $22,500 (design) • Timeline: Construction began as of mid-September • Funding source: Montgomery County road bond
• Cost: $10,500 (design) • Timeline: June-August (design), fall-TBD (construction) • Funding source: Montgomery County road bond 3 Lake Woodlands Drive at Gosling Road intersection improvements Project: The project will extend turn lanes to improve mobility and safety from eastbound Lake Woodlands Drive onto northbound Gosling Road and from westbound Lake Woodlands Drive onto southbound Gosling Road. Update: Engineering design was almost done in mid- September, Montgomery County Precinct 3 officials said. • Cost: $40,000 (design) • Timeline: June-early September (design) • Funding source: Montgomery County road bond 4 Research Forest Drive at Gosling Road turn-lane extension Project: The project will extend dual left-turn lanes from westbound Research Forest to southbound Gosling Spring 99 TOLL
Upcoming projects
1 Grogans Mill Road at Research Forest Drive right-turn improvements Project: The project will extend a right-turn lane from northbound Grogans Mill Road onto eastbound Research Forest Drive. Update: Engineering design was nearing completion in mid-September and construction will begin in the fall. • Cost: $50,000 (design) • Timeline: June-August (design), fall-TBD (construction) • Funding source: Montgomery County road bond 2 Research Forest Drive at Greenbridge Drive turn-lane extension Project: The project will extend and widen the left- turn lane from eastbound Research Forest Drive to northbound Greenbridge Drive. Update: Engineering design was nearing completion in mid-September and construction will begin this fall.
Completed projects
7 Lake Woodlands Drive at East Panther Creek Drive turn-lane extension Project: The project extends the left-turn lane from westbound Lake Woodlands Drive onto southbound East Panther Creek Drive. Update: Engineering design was completed in August. Construction was completed in September. • Cost: $22,500 (design), $116,057 (construction) • Timeline: June-September • Funding source: Montgomery County road bond
cabinet remodels under $5,000 15% OFF 20% OFF cabinet remodels $5,000 or more FREE Design Consultation! Call for your
SMART CABINETS.
Kitchens, Bathrooms & Custom Designs Free In-Home Design Consultations Professional, Precise Installation Locally Owned. Nationally Recognized.
Discounts given after estimate
STUNNING RESULTS.
346-536-4664 | www.cabinetiq.com/woodlands
37
THE WOODLANDS EDITION
Powered by FlippingBook