Transportation
BY LIZZY SPANGLER
Upcoming projects
Willis
6
Montgomery
1097
1 I-45, South Loop 336 signal reconstruction Project: The traffic signal will be reconstructed after being damaged in a traffic accident. Update: Conroe City Council voted Nov. 13 to award a contract to Third Coast Services LLC for the project.
7
BLUEBERRY HILL
LONE STAR PKWY.
LAKE CONROE HILLS DR.
75
2432
830
ATKINS CREEK
LAKE CONROE
• Timeline: TBD • Cost: $100,479 • Funding source: city of Conroe
1484
105
149
Ongoing projects
2854
3
N. 10TH ST.
2 Hwy. 75 improvements Project: Hwy. 75 is undergoing improvements that include planing and underseal base repair. Update: This project is 94% completed, per a Nov. 10 update from the Texas Department of Transportation. • Timeline: first quarter 2025-first quarter 2026 • Cost: $3.3 million • Funding source: state funds 3 Hwy. 105 widening Project: Hwy. 105 is being widened from two to four lanes between 10th Street and South Loop 336. Update: According to a Nov. 10 media update from TxDOT, this project is 53% completed. • Timeline: March 2023-second quarter 2028 • Cost: $52.65 million • Funding source: state funds 4 I-45 high-occupancy vehicle lane extension Project: The HOV lane of I-45 is being extended. Update: Construction is 79% completed for this project, according to TxDOT’s Nov. 10 media update. • Timeline: second quarter 2025-fourth quarter 2025 • Cost: $1.3 million • Funding sources: federal, state funds 5 South Loop 336 widening Project: Between I-45 and Ladera Creek Trace, South Loop 336 is being widened from two to four lanes.
KEENAN CUT OFF RD.
LADERA CREEK TRACE
GLADSTELL ST.
2
Conroe
336
3083
1
5
FISH CREEK THOROUGHFARE
4
1314
149
WEST FORK SAN JACINTO RIVER
1488
45
242
MAP NOT TO SCALE N
Update: This project is 52% completed. • Timeline: November 2024-third quarter 2027 • Cost: $20.57 million • Funding source: state funds 6 FM 1097 widening Project: FM 1097 is widening from two to four lanes. Update: Work on this project is 83% completed, according to a Nov. 10 media update from TxDOT. • Timeline: second quarter 2022-second quarter 2026
• Cost: $20.21 million • Funding sources: federal, state funds 7 FM 1097 at Atkins Creek project Project: Work is underway for a project that includes culvert replacement, shoulder addition and overlay. Update: According to TxDOT’s Nov. 10 media update, this project is 32% completed. • Timeline: third quarter 2025-third quarter 2026 • Cost: $4.41 million • Funding sources: federal, state funds
COMMERCIAL CONSTRUCTION • NEW BUILDS • REMODELS • EXPANSIONS
25 years of experience delivering commercial projects for clinics, gyms, churches, shopping centers, barndominiums and more.
START YOUR PROJECT TODAY, CALL (281) 520-7716 or VISIT RMACGC.COM
11
CONROE - MONTGOMERY EDITION
Powered by FlippingBook