Frisco | April 2026

Transportation

BY JACQUELYN BURRER

4 Legacy Drive construction Project: Legacy Drive will see construction from Main Street to Panther Creek Parkway. Update: The project is currently in the design phase, with construction expected to now begin mid 2027. • Timeline: mid 2027-mid 2029 • Cost: $23 million • Funding sources: city of Frisco, external funding 5 Meadow Hill Drive reconstruction Project: Meadow Hill Drive will be reconstructed from North County Road to Rogers Road. The project will also include adding two roundabouts. Update: The project is currently in the design phase. • Timeline: spring 2026-mid 2027 • Cost: $3.7 million • Funding source: city of Frisco 6 Ohio Drive roundabout Project: A roundabout will be added to the Ohio Drive and Wade Boulevard intersection. Update: The project is in the planning phase.

7 Panther Creek Parkway widening Project: Panther Creek Parkway is set to be widened from a four-lane roadway to a six-lane roadway from Preston Road to Coit Road. Update: The project is in the planning phase. • Timeline: mid 2027-late 2029 • Cost: TBD • Funding source: TBD

10 Mahard Parkway construction Project: The project will construct a six-lane roadway from PGA Parkway to US 380. Update: The project has been under construction since 2024 and is expected to be completed later this year. • Timeline: late 2024-late 2026 • Cost: $11.03 million • Funding source: city of Frisco 11 PGA Parkway construction Project: PGA Parkway is being constructed to a six-lane divided roadway from Preston Road to Coit Road. Update: The project is under construction and expected to be completed near the end of the year. • Timeline: late 2024-mid 2026 • Cost: $31.1 million • Funding sources: city of Frisco, external funding 12 Teel Parkway widening Project: Teel Parkway is being widened from Stafford Middle School to Olive Branch Drive. It is being widened from a two-lane divided roadway to a four-lane divided roadway. Update: Construction is now expected to wrap up early next year. • Timeline: fall 2025-early 2027 • Cost: $9.36 million • Funding sources: city of Frisco, external funding

Upcoming projects

MAHARD PKWY.

UNIVERSITY DR.

380

PGA PKWY.

10

1 Frisco Street construction Project: Frisco Street will be constructed from Eldorado Parkway to Panther Creek Parkway into a four-lane divided roadway. Update: The project is in the design phase. • Timeline: spring 2026-mid 2027 • Cost: $15 million Project: Hillcrest Road will be updated from SH 121 to Main Street, but project details are not yet available. Update: The project is in the design phase. • Timeline: fall 2027-late 2028 • Cost: $12 million • Funding source: city of Frisco 3 John Hickman Parkway Project: John Hickman Parkway will be expanded from Dallas North Tollway to Parkwood Boulevard. Update: The project is in the design phase with construction expected to begin in 2027. • Timeline: early 2027-spring 2028 • Cost: $7.5 million • Funding source: city of Frisco • Funding source: city of Frisco 2 Hillcrest Road updates

ROCKHILL PKWY.

289

11

FIELDS PKWY.

VIRGINIA PKWY.

OLIVE BRANCH RD.

12

7

8

PANTHER CREEK PKWY.

LEWISVILLE LAKE

1

2478

HILLCREST RD.

COBB HILL DR.

ELDORADO PKWY.

Ongoing projects

5

4

8 Hillcrest Road construction Project: Hillcrest Road is being constructed into a four- lane divided roadway from Panther Creek Parkway to PGA Parkway. Update: The project is nearing completion. • Timeline: early 2024-fall 2026 • Cost: $5.99 million Project: King Road will be widened to a three- and four- lane concrete roadway from Rose Lane to Witt Road. Update: Westbound King Road is set to see closures. • Timeline: late 2025-spring 2027 • Cost: $12.5 million • Funding sources: city of Frisco, external funding • Funding source: city of Frisco 9 King Road widening

ROGERS RD.

KING RD.

MEADOW HILL DR.

MAIN ST.

STONEBROOK PKWY.

9

Frisco

2

ROLATER RD.

DNT TOLL

WADE BLVD.

423

6

LEBANON RD.

3

SRT TOLL

• Timeline: TBD • Cost: $4 million • Funding source: city of Frisco

GAYLORD PKWY.

JOHN HICKMAN PKWY.

WARREN PKWY.

PARKWOOD BLVD.

N MAP NOT TO SCALE

LITTLE ELM 27100 Hwy 380 (972) 347-9630

LOWRY 4100 E US 380 (972) 540-2500 THE COLONY 4901 Hwy 121 (214) 469-2113

ALLEN 1839 N Central Expressway (972) 908-3488

Powered by