Transportation
BY HEATHER MCCULLOUGH
NORTHLAKE
T E A S L E Y L N .
Upcoming projects
OAK ST.
LAKELAND DR.
3
1384
1830
1 Timber Valley Drive and Faireld Lane reconstruction Project: Both projects include the replacement of the street, sidewalks, sewer lines and water lines. The 1A Timber Valley project will take place between Cross Timbers Road and River Oaks Drive. 1B Faireld Lane construction will occur between Timber Valley and Summer Trail. Update: Town ocials planned to send the project out to bid in February. • Timeline: spring 2026-summer 2027 • Cost: $6.93 million • Funding source: town of Flower Mound 2 FM 407 widening project Project: The road will be widened from two lanes to six lanes between Bill Cook Road and FM 1830. A shared-use path and sidewalk will also be included to accommodate bicyclists and pedestrians. Update: The public hearing on the project scheduled for Jan. 29 was postponed due to Winter Storm Fern, and updated information will be provided once the meeting is rescheduled. • Timeline: TBD • Cost: $171 million • Funding source: Texas Department of Transportation ROANOKE 5 T H S T . JUSTIN 156
HIGHLAND VILLAGE RD.
377
CEDAR DR.
5
2
156
LEWISVILLE LAKE
SELLMEYER LN.
MEDINA DR.
407
EDGEWOOD DR.
35E
MERRIMAN DR.
35W
BILL COOK RD.
GAYLE LN.
JUSTINRD.
35E
407
Highland Village
Bartonville
2499
BRIDLEWOOD BLVD.
C O L L E G E P K W Y .
WAKETON RD.
RIDGECREST DR.
377
4
Flower Mound
SUNSET TRL.
ROCKY POINT RD.
FLOWER MOUND RD.
114
CROSS TIMBERS RD.
GRAPEVINE LAKE
3040
TIMBER VALLEY DR.
1A
Westlake
LAKESIDE PKWY.
SUMMER TRL.
170
1B
FAIRFIELD LN.
MAP NOT TO SCALE N
Ongoing projects
5 FM 407 and I35W intersection improvements
• Timeline: July 2025-March 2026 • Cost: $1.9 million • Funding source: city of Highland Village 4 Sunset Trail
3 Highland Village water line replacements, sewer installation
Project: Work includes adding right-turn lanes on the west side of FM 407 and I-35W to improve congestion. The project also includes adding drainage, vehicle deection walls at the FM 407 and I-35W overpass and pavement markings. Update: The Denton County Commissioners Court approved a construction contract with Ed Bell Construction Company during its regular meeting Jan. 30. • Timeline: Construction will begin in February and will take 100 days to complete. • Cost: $3.03 million • Funding source: Denton County
Project: Work crews are replacing water lines along several neighborhood streets in Highland Village. Through the project, about 6,800 feet of new water line and 600 feet of new storm sewer pipes, will be installed. The six streets aected by the project are: Cedar Drive, Edgewood Drive, Merriman Drive, Lakeland Drive and Gayle Lane. Update: The contractor has completed installation of the water main on Merriman Drive and Gayle Lane, and has moved to install the sewer pipe on Gayle Lane and water line on Oak Street, according to a city news release from early February.
Project: Work includes replacing the 48-inch water pipe under Sunset Trail, between Rocky Point and Ridgecrest Drive. Crews will also complete other drainage work in the area. Update: A road closure along Sunset between Rocky Point and Ridgecrest is expected to end in mid- February. • Timeline: Jan. 27-March 20 • Cost: $50,000 • Funding source: town of Flower Mound
10
COMMUNITYIMPACT.COM
Powered by FlippingBook