Prosper - Celina | January 2026

Transportation

BY JACQUELYN BURRER

455

• Timeline: January 2026-July 2026 • Cost: $1.7 million • Funding source: city of Celina 6 Prosper Trail construction

9,100 feet of 30-inch waterline and 3,100 feet of 8-inch wastewater line, according to town documents. Update: At a Nov. 25 meeting, Prosper Town Council approved a $1 million contract with Freese and Nichols Inc. to design a project relocating water and wastewater lines along US 380 between Coit and Custer roads.

Ongoing projects

Upcoming projects

SUNSET BLVD.

E . M A

428

8 Sunset Boulevard asphalt improvements Project: The asphalt pavement along Sunset Boulevard from Preston Road to Coit Road will be replaced. Update: The project is at 80% completion. • Timeline: estimated completion January 2026 • Cost: $4.2 million • Funding source: city of Celina 9 US 380 widening Project: TxDOT is widening US 380 from the Collin and Denton County line to Loop 288 from four lanes to six lanes. Update: Traffic switches are ongoing along US 380. • Timeline: January 2022-March 2026 • Cost: $175.66 million • Funding source: TxDOT, other entities 10 Coit Road construction Project: The first phase of the project, which spans Coit Road from First Street to Prosper Trail, will design and construct four lanes of an ultimate six-lane roadway. Update: The project is expected to wrap up this summer. • Timeline: summer 2025-summer 2026 • Cost: $19.85 million • Funding source: town of Prosper

1 First Street traffic signal addition Project: A new traffic signal will be added to the future intersection of First Street and Legacy Drive. The proposed intersection improvements include a signal with pedestrian ramps and straight crosswalks. Update: Town Project Manager Joshua Cotton said the project is underway, with permanent signal materials

Celina

8

7

Project: Prosper Trail will be reconstructed from Coit Road to Custer Road and the bridge will be replaced at the Wilson Creek crossing. It will be a four-lane divided roadway. Update: The project is in the design phase and construction has been delayed to start in summer 2028 to align with the Upper Trinity Regional Water District’s treatment plant expansion. • Timeline: summer 2028-summer 2029 • Cost: $13.45 million • Funding source: town of Prosper 7 Oklahoma Drive construction Project: Oklahoma Drive will be reconstructed from Pecan Street to Malone Street by replacing the existing asphalt construction with two concrete lanes and other improvements. Update: The project is waiting on utility relocations. • Timeline: estimated completion by September 2026 • Cost: $3.04 million • Funding source: city of Celina

2

N. OKLAHOMA DR.

• Timeline: TBD • Cost: $1 million • Funding source: town of Prosper 4 First Street widening

S. CELINA PKWY.

E. OUTER LOOP

expected to arrive by March. • Timeline: March 2026-TBD • Cost: $990,818 • Funding source: town of Prosper 2 Celina Parkway reconstruction

428

Project: First Street will be widened from a two-lane rural roadway to a four-lane divided suburban roadway from Dallas North Tollway to Coleman Street. Update: The project is expected to start construction in March. • Timeline: spring 2026-fall 2027 • Cost: $27.79 million • Funding source: town of Prosper 5 Frontier Parkway waterline reconstruction Project: This project will replace existing water lines along Frontier Parkway from east of Preston Road to Coit Road. The work is being completed due to the Texas Department of Transportation project to widen Frontier Parkway from Preston Road to Custer Road. Update: Construction is expected to start in January.

6

5

1385

FRONTIER PKWY.

Project: The project will reconstruct Celina Parkway with an asphalt overlay from FM 428 to the Collin County Outer Loop. Update: Celina City Council members approved on Dec. 9 a $1.75 million contract to repair and resurface Celina Parkway. • Timeline: early 2026-June 2026 • Cost: $2.62 million • Funding source: city of Celina 3 US 380 waterline reconstruction Project: The project stretches along US 380 from Coit Road to Custer Road. Work will include replacing roughly

PARVIN RD.

6

E. PROSPER TRL.

Prosper

10

4

1

FIRST ST.

9

3

LOVERS LN.

380

UNIVERSITY DR.

MAP NOT TO SCALE N

423

PGA PKWY.

VIRGINIA PKWY.

289