5 Rockride Lane upgrades Project: Rockride Lane is being upgraded to a two- lane collector with a continuous center left-turn lane and a 10-foot-wide shared-use path from SE Inner Loop to Sam Houston Avenue. Update: The contractor completed the west side of the road and began working on the east side. The city expects substantial completion by the
SE INNER LOOP
2
35
SOUTHWEST BYPASS
1460
ROCKRIDE LN.
5
SAM HOUSTON AVE.
N
MAP NOT TO SCALE
end of September. • Timeline: 2022-26 • Cost: $12 million • Funding source: city of Georgetown
• Timeline: 2022-28 • Cost: $70.6 million • Funding sources: city of Georgetown, Georgetown Transportation Enhancement Corporation
Upcoming projects
1 Williams Drive medians Project: The project will construct medians with turn lanes on Williams Drive from I-35 to Serenada Drive, including a shared-use path on the north side of the road. Update: The Texas Department of Transportation is reviewing contractor bids, and ocials anticipate construction starting this summer. • Timeline: 2023-27 • Cost: $18.6 million • Funding sources: city of Georgetown, trafic impact fees, federal grants, tax increment inancing 2 SE Inner Loop widening Project: A 2.91-mile stretch of SE Inner Loop will be widened to a four-lane, divided road from Hwy. 29 to FM 1460. A shared-use path will be added. Update: Utility relocations are under way from FM 1460 to Southwestern Boulevard.
Update: All four lanes are open to trac, with ancillary work remaining.
Ongoing projects
• Timeline: 2023-26 • Cost: $29.6 million • Funding source: city of Georgetown 6 Austin Avenue vehicular bridges
3 Shell Road widening Project: The city will widen Shell Road from Williams Drive to Sycamore Street to four lanes with a raised median, shared-use path, and left- and right-turn lanes. Update: As of May, crews were working on utility installation as well as some road and signal work.
Project: This project includes reconstruction of two vehicular bridges crossing the San Gabriel River. Update: The southbound Austin Avenue bridge decks were demolished starting in early June, and reconstruction will take approximately two months. The contractor will then do the northbound bridge decks. • Timeline: 2024-27 • Cost: $12.8 million • Funding sources: city of Georgetown, developer fees
• Timeline: 2022-27 • Cost: $18.17 million • Funding source: city of Georgetown 4 DB Wood Road widening Phase 1
Project: The project adds four lanes, a center turn lane and a shared-use path from Hwy. 29 to Oak Ridge Road.