Frisco | March 2026

Transportation

BY SAMANTHA DOUTY

4 Warren Parkway upgrades Project: Warren Parkway will be updated from Legacy Drive to Internet Boulevard. Update: The project is in the design phase and project details are not yet available. • Timeline: early 2027-mid 2028 • Cost: $4.2 million • Funding source: city of Frisco 5 Rolater Road improvements Project: The project will space Rolater Road from Preston Road to Kings Ridge Road. Update: The project is in the planning phase and project details are not yet available. • Timeline: TBD • Cost: TBD • Funding source: TBD 6 Ohio Drive roundabout addition Project: A roundabout will be added to the Ohio Drive and Wade Boulevard intersection. Update: The project is in the planning phase and is expected to start construction next year. • Timeline: early 2027-early 2028 • Cost: $4 million • Funding source: city of Frisco

• Cost: $9.36 million • Funding source: city of Frisco, external funding 10 PGA Parkway construction Project: The project will construct a six-lane divided roadway from Preston Road to Coit Road. Update: The project is under construction and is expected to be completed later this year. • Timeline: late 2024-mid 2026 • Cost: $31.1 million • Funding source: city of Frisco, external funding 11 Lebanon Road widening Project: Lebanon Road is being widened from a four- land divided roadway to a six-lane divided roadway from FM 423 to Todd Drive. Update: The project is under construction. • Timeline: mid 2025-late 2027 • Cost: $23 million • Funding source: city of Frisco, external funding 12 Fields Parkway traffic light addition Project: A traffic light is being installed at the Fields Parkway and Dallas Parkway intersection. Update: The project is in its last months of construction. • Timeline: mid 2025-mid 2026 • Cost: $350,000 • Funding source: city of Frisco

Upcoming projects

Ongoing projects

MAHARD PKWY.

UNIVERSITY DR.

380

PGA PKWY.

7

1 Legacy Drive updates Project: Legacy Drive will be updated from Main Street to Panther Creek Parkway. Update: The project is in the planning phase and details regarding the project are not yet available. • Timeline: mid 2027-mid 2029 • Cost: $23 million • Funding source: city of Frisco, external funding 2 Panther Creek Parkway widening Project: Panther Creek Parkway will be widened from a four-lane roadway to a six-lane roadway from Preston Road to Coit Road. Update: The project is in the planning phase. • Timeline: mid 2027-late 2029 • Cost: TBD • Funding source: TBD 3 Hillcrest Road construction Project: The project will construct a four-lane divided roadway from Eldorado Parkway to Main Street. Update: The project is in the planning phase. • Timeline: early 2028-mid 2029 • Cost: TBD • Funding source: TBD

7 Mahard Parkway construction Project: Mahard Parkway is being constructed to a six- lane roadway from PGA Parkway to US 380. Update: The project is under construction and expected to be completed later this year. • Timeline: late 2024-late 2026 • Cost: $11.03 million • Funding source: city of Frisco 8 Dallas Parkway widening Project: Dallas Parkway is being updated to include additional lanes on northbound and southbound frontage roads from Panther Creek Parkway to PGA Parkway. Update: The project is under construction and is expected to wrap this year. • Timeline: early 2025-mid 2026 • Cost: $18.39 million

ROCKHILL PKWY.

289

10

FIELDS PKWY.

VIRGINIA PKWY.

12

OLIVE BRANCH RD.

9

2

8

PANTHER CREEK PKWY.

LEWISVILLE LAKE

2478

HILLCREST RD.

ELDORADO PKWY.

1

3

KING RD.

MAIN ST.

STONEBROOK PKWY.

KINGS RIDGE RD.

Frisco

5

ROLATER RD.

DNT TOLL

WADE BLVD.

423

11

• Funding source: city of Frisco 9 Teel Parkway widening

6

TODD DR.

WARREN PKWY.

LEBANON RD.

SRT TOLL

Project: Teel Parkway is being widened from a two-lane divided roadway to a four-lane divided roadway from Stafford Middle School to Olive Branch Road. Update: The project is under construction. • Timeline: mid 2025-early 2027

GAYLORD PKWY.

4

HILLCREST RD.

INTERNET BLVD.

PARKWOOD BLVD.

N MAP NOT TO SCALE

LITTLE ELM 27100 Hwy 380 (972) 347-9630

LOWRY 4100 E US 380 (972) 540-2500 THE COLONY 4901 Hwy 121 (214) 469-2113

ALLEN 1839 N Central Expressway (972) 908-3488

Powered by