138
Transportation
BY GRANT CRAWFORD & MANUEL HOLGUIN JR.
45 TOLL
Upcoming project
Hutto
130 TOLL
INNOVATION BLVD.
6
2
MOORLYNCH AVE.
130 TOLL
PFLUGER FARM LN.
LIMMER LOOP
TOWN CENTER DR.
PARKWAY DR.
1
Pflugerville
3
35
685
HELIOS WAY
1 Kelly Lane Phase 3 Project: The city will reconstruct about 1.3 miles of Kelly Lane between Moorlynch Avenue and Weiss Lane, expanding the roadway from a two-lane road into a four-lane divided arterial, with four roundabout intersections. Update: Project to go out to bid this spring • Timeline: Completion planned for early 2030 • Cost: $31.5 million • Funding source: city bond funds
5A
130 TOLL
IMPACT WAY
4
CAMERON RD.
5B
MAP NOT TO SCALE
N TM; © 2026 COMMUNITY IMPACT CO. ALL RIGHTS RESERVED.
drainage, sidewalks and streetlights. Update: In final design and bidding preparation phase • Timeline: Expected to go out to bid in May • Cost: $3.4 million • Funding source: roadway impact fees, city bonds, community development block grant
portion of B Impact Way will be extended south. Update: Phase 2 of Helios Way is underway. • Timeline: Completion expected in mid-May • Cost: $5.8 million • Funding source: PCDC type B Sales Tax Hutto
Pflugerville
Ongoing projects
Upcoming projects
Ongoing projects
4 East Pflugerville Parkway Realignment Project: A 1-mile extension of East Pflugerville Parkway, from Weiss Lane to Jesse Bohls Drive, will include a four-lane roadway with a center median. Update: Construction began Jan. 12. • Timeline: Final completion expected in May 2027 • Cost: $10.7 million • Funding source: city bonds, roadway impact fees 5 Helios Way, Impact Way improvements Project: A connection from A Helios Way to the SH 130 frontage road is under construction, after which a
2 Pfluger Farm Lane North improvements Project: A section of Pfluger Farm Lane will be widened and extended into a three-lane road. Update: Design is about 95% complete. • Timeline: Expected to bid in September • Cost: $6.5 million • Funding source: city bond funds, roadway impact fees 3 Parkway Drive reconstruction Project: Parkway Drive will be reconstructed into an urban road section with pavement, curb, gutter
6 Innovation Boulevard and Limmer Loop traffic signal Project: Construction crews are installing a traffic signal at Innovation Boulevard and Limmer Loop. Update: Oncor is finalizing the remaining electrical work, after which the signal will operate in flashing mode before transitioning into a functional traffic light. • Timeline: An exact timeline is TBD • Cost: $2.23 million • Funding source: capital projects fund
TOGETHER WE CAN MAKE A DIFFERENCE IN OUR COMMUNITY! HOURS: Monday through Saturday 10 am to 4 pm Donations Accepted: Monday - Saturday 8am - 4pm TREASURES
CHARITY RESALE SHOP & BOUTIQUE
DONATE ONLINE AT RRASC.ORG
1075 E Main Street, Round Rock 78664
19
PFLUGERVILLE - HUTTO EDITION
Powered by FlippingBook