BY JACQUELYN BURRER
• Cost: $3.26 million • Funding source: city of Plano 3 Custer Road
concrete before sealing with a protective layer. The process aims to expand the road’s lifespan. Update: Arterial concrete repairs on Custer Road from Hedgcoxe Road to Spring Creek Parkway began Aug. 27. • Timeline: August 2025-October 2026 • Cost: $1.63 million • Funding source: city of Plano 6 Coit Road asphalt overlay Project: Concrete replacement and arterial overlays. Update: Arterial concrete repairs began Aug. 13 along Coit Road from SH 190 to Parker Road. • Timeline: July 2025-July 2026 • Cost: $1.611 million • Funding source: city of Plano 7 Parker Road asphalt overlay Project: Concrete replacement and arterial overlays. Update: Arterial concrete repairs from Country Place Road to Independence Parkway are estimated to complete in spring 2026. • Timeline: August 2024-spring 2026 • Cost: $4.37 million • Funding source: city of Plano
Completed projects
8 Alma Drive asphalt overlay Project: Concrete replacement and arterial overlays. Update: Road paving from Parker Road to Hedgcoxe Road finished in September. • Timeline: May 2025-September 2025 • Cost: $6.60 million • Funding source: city of Plano 9 Midway Road asphalt overlay Project: Concrete replacement and arterial overlays. Update: Road paving from Spring Creek Parkway to Park Boulevard finished in September. • Timeline: Fall 2024-September 2025 • Cost: $6.60 million • Funding source: city of Plano 10 Park Boulevard asphalt overlay Project: Concrete replacement and arterial overlays. Update: final cleanup work for arterial concrete repairs on Park Boulevard between Plano’s west city limits and
Project: The North Texas Municipal Water District is currently working to replace an aging pipeline along Custer Road. Update: Construction will cause lane closures on sections of Custer Road with work scheduled Monday- Friday from 9 a.m.-4 p.m. • Timeline: February 2025-October 2026 • Cost: $18 million • Funding source: North Texas Municipal Water District 4 Park Boulevard water rehabilitation project Project: The two-phase project, stretching from Preston Road to Plano’s east city limits combined, is working to replace the waterlines running under Park Boulevard. Update: The first phase from Preston Road to U.S. 75 has been delayed to finish in December. • Timeline: September 2024-December 2025 • Cost: $9.58 million • Funding source: city of Plano 5 Custer Road asphalt overlay Project: Crews are undergoing the arterial overlay process, which consists of replacing sections of
Preston Road completed in October. • Timeline: April 2024-October 2025 • Cost: $2.085 million • Funding source: city of Plano
19
PLANO SOUTH EDITION
Powered by FlippingBook