Cedar Park - Far Northwest Austin Edition | October 2025

Transportation

BY STEVE GUNTLI

Upcoming projects

Leander

1 Intersection improvements from Whites- tone Boulevard to 183A Toll Project: This project will improve vehicular, cyclist and pedestrian safety. Update: Pre-design phase • Timeline: Expected winter 2026 • Cost: $2.57 million • Funding Source: 2022 bond 2 Toro Grande Boulevard Expansion North and South Project: The north section from RM 1431 to New Hope Drive will receive intersection and signal improvements, turn lanes and utility upgrades. The south section will connect RM 1431 south and west to Parmer Lane, and extend Toro Grande Boulevard from Whitestone

183A TOLL

BLOCK HOUSE DR.

3

TORO GRAND BLVD.

SCOTTSDALE DR.

4

183

2

1431

1

VISTA RIDGE BLVD.

5

183

Boulevard to New Hope Drive. Update: Contractors selected • Timeline: Expected spring 2027 • Cost: $36.5 million • Funding Source: 2022 bond

734

6

.

ANDERSON MILL RD.

AVERY RANCH BLVD.

3 Hwy. 183 at Scottsdale dedicated U-turn Project: This project will shift southbound through lanes west and construct a new right turn lane at Scottsdale Drive. Update: Recommendation for professional engineering

STAKED PLAINS DR.

Cedar Park

services approved by council Sep. 11 • Timeline: Expected winter 2027 • Cost: $1.3 million • Funding Source: 2022 bond

45 TOLL

MAP NOT TO SCALE

N TM; © 2025 COMMUNITY IMPACT CO. ALL RIGHTS RESERVED.

620

4 New Hope Drive expansion at Block House to CR 180 & 183A Toll innovative intersection Project: The road will expand from four to six lanes and add an innovative intersection design at 183A Toll. Update: Road expansion north of New Hope Drive and

5 RM 1431 expansion from New Hope Drive to Bagdad Road Project: This project will widen two miles of the roadway and expand the four-lane roadway to six-lane. Update: Currently in design phase • Timeline: Construction expected winter 2027 • Cost: $8.15 million • Funding Source: 2022 bond

Ongoing projects

6 183A Toll frontage roads Project: This project will add two lanes on either side of 183A Toll from E. Whitestone Boulevard to Avery Ranch Boulevard. Update: Project began construction this summer • Timeline: Expected completion 2029 • Cost: $139 million • Funding Source: Texas Department of Transportation

innovative intersection in process. • Timeline: Expected winter 2027 • Cost: $2.5 million • Funding Source: 2022 bond

Relieve foot and ankle pain, restore function, and start moving comfortably again with the help of our podiatry care team. Get back on your feet

• Bunion correction • Foot fractures & injuries

• Surgical & non-surgical options • All ages seen: children to adults

Book now at ARCpodiatry.com

Location near you at ARC Cedar Park Building B

17

CEDAR PARK - FAR NORTHWEST AUSTIN EDITION

Powered by